HINREN Our Solutions
919035625364
CUSTOMER

Mr M.G.Mukunda

PROJECT CATEGORY

Hybrid Solar

COMPLETED

2017-10-30T00:00:00

PROJECT BUDGET

18,00,000

PROJECT DESCRIPTION

Rooftop Solar

CUSTOMER REQUIREMENT

Client wanted to run all the loads on solar power. Client did not want any kind of power disruptions . Client also wanted to export any excess power generated back into the grid under net metering

WHAT WE DID

We installed a 9.8 KW Hybrid solar system together with a 1.6 KW off grid system. 8 Nos of 200 Ah batteries is connected to the setup for full back-up

RESULT

Client has never faced a power failure till date . All the loads including the ones on 3 phase run on solar power. Power produced is in fact a little excess than the requirement. So the excess energy is exported to the state power utility. In terms of numbers, the system produces approximately 17,600 units of electricity every year.