Customer:
Gopalan Habitat Splendor
Project Category:
RWH : Apartment
Customer Requirement:
The Tube-wells in the Apartment Complex were drying up and the demand for water was going up. Customer wanted to be ready for any eventuality of tube-wells completely drying up. They were also facing some flooding issues during monsoon since the run off had no place to go. So they wanted to install the Rainwater harvesting unit to use as much rooftop rainwater as possible and also check the run-off
Project Result:
7800,000 Liters of water & 12,500 units of electricity saved every year .
What we did:
The project was divided into three phases. Each wing was one phase. In each phase, the balcony water was isolated. The rooftop rainwater was conveyed into first rain separation units , Sedimentation units and finally to filtartion units . The filtered water was stored in the UG sump
Project Description
Rainwater Harvesting
Project Budget:
10,50,000
Completion Date:
2011-05-31T00:00:00