Customer:
Mr M.G.Mukunda
Project Category:
Solar : Hybrid
Customer Requirement:
Client wanted to run all the loads on solar power. Client did not want any kind of power disruptions . Client also wanted to export any excess power generated back into the grid under net metering
Project Result:
Client has never faced a power failure till date . All the loads including the ones on 3 phase run on solar power. Power produced is in fact a little excess than the requirement. So the excess energy is exported to the state power utility. In terms of numbers, the system produces approximately 17,600 units of electricity every year.
What we did:
We installed a 9.8 KW Hybrid solar system together with a 1.6 KW off grid system. 8 Nos of 200 Ah batteries is connected to the setup for full back-up
Project Description
Rooftop Solar
Project Budget:
18,00,000
Completion Date:
2017-10-16T00:00:00
