Customer:
Sherwood Apartments
Project Category:
RWH : Apartment
Customer Requirement:
Kaggadasapura like many other areas in Bangalore is heavily dependant on borewells which are fast drying up . Realising this , The Apartment association wanted to harvest maximum possible rainwater so that their dependence on bore wells or tanker water comes down .
Project Result:
932,000 Liters of water Harvested Every year
What we did:
Entire roof-top rainwater run off was captured , initially before filtration, water was passed through a sedimentation tank , the overflow from the sedimentation tank was put through three rounds of filtration and stored in the underground sump for normal usage.
Project Description
Rainwater Harvesting
Project Budget:
2,25,000
Completion Date:
2009-11-26T00:00:00